ECRL Maran-Kota Bharu track completed 2.5 months ahead of schedule, progress in Kelantan now past 88%

ECRL Maran-Kota Bharu track completed 2.5 months ahead of schedule, progress in Kelantan now past 88%

The 400-km East Coast Rail Link (ECRL) track from Maran, Pahang to Kota Bharu, Kelantan has been completed two and a half months ahead of schedule, Malaysia Rail Link (MRL) CEO Datuk Seri Darwis Abdul Razak has said, according to a Bernama report.

The ECRL project in Kelantan, which includes the Kota Bharu station (for passengers only) in Bandar Baru Tunjong and the Pasir Puteh station (for goods and passengers) in Cherang Tuli, is 87.8% complete as of December. The figure is expected to rise with said completion of the main rail installation, and both stations are expected to be completed by 2026’s second quarter.

ECRL Maran-Kota Bharu track completed 2.5 months ahead of schedule, progress in Kelantan now past 88%

“This will speed up the construction of the electrification system, signalling and telecommunications for the 43.86 km stretch in Kelantan,” Darwis said, adding that the transport ministry will announce fares at a later juncture and that minister Anthony Loke has assured that ticket prices would be “reasonable” and would not burden the rakyat.

Built by China Communications Construction ECRL (CCCECRL), the 665-km line will connect the East Coast states of Kelantan, Terengganu and Pahang to Port Klang, Selangor on the West Coast. The Kota Bharu-Gombak Terminal line – a four-hour journey – is set to be completed in December 2026 and be operational by January 2027.

ECRL Maran-Kota Bharu track completed 2.5 months ahead of schedule, progress in Kelantan now past 88%

CRRC Dalian has allocated 11 six-car electric multiple units (EMU) – the first of which is expected to arrive by end-2025 – that can each carry 430 passengers and hit 160 km/h. It will also provide two electric locomotives – which will be assembled at the Kuantan Port City depot – to pull goods trains.

For over 100 years, the Negeri Sembilan town of Gemas has been the one and only ‘rail gateway to the east’ via Keretapi Tanah Melayu Berhad’s (KTMB) East Coast Line intercity services (known in tourist circles as the ‘Jungle Train’; prone to cancellations caused by floods). Thanks to ECRL, we’ll soon be able to go by train to the East Coast without leaving Selangor.

Looking to sell your car? Sell it with Carro.

Certified Pre-Owned - 1 Year Warranty

10% discount when you renew your car insurance

Compare prices between different insurer providers and use the promo code 'PAULTAN10' when you make your payment to save the most on your car insurance renewal compared to other competing services.

Car Insurance

Jonathan James Tan

While most dream of the future, Jonathan Tan dreams of the past, although he's never been there. Fantasises much too often about cruising down Treacher Road (Jalan Sultan Ismail) in a Triumph Stag that actually works, and hopes this stint here will snap him back to present reality.

 

Comments

  • Red Bean Army on Jan 16, 2025 at 2:38 pm

    Lol yet another white elephant by the ccp

    Like or Dislike: Thumb up 4 Thumb down 24
    • Elon Musk Sr on Jan 17, 2025 at 5:48 pm

      When DrM defeated the birkin bandit,he almost fainted when he discovered the ECRL contract.He knew it was worst than a white elephant,but we have to honour the lopsided contract.So,why r people so negative when we say it is a white elephant?Sympathise with the bandit?Come on,no more”can I advice u something”.

      Like or Dislike: Thumb up 4 Thumb down 3
  • Lets See on Jan 16, 2025 at 3:38 pm

    #FireLoke
    #LokePlsStepDown
    #FancyPlateSellerNo1
    #PreviousTMinisterWasBetter

    Like or Dislike: Thumb up 5 Thumb down 21
  • herewego on Jan 16, 2025 at 4:40 pm

    The progress with the track laying machine CCPG-500A is absolutely fast for the ECRL project. Although for CURRENT is single track in double track formation operation during 2027 later, I believed that the demand will be increase for east coast travel due to time saving for long haul travelling. If the demand increases drastically, the track can be lay in no time within 3-months with addon ballast, electrification, and additional signalling materials. We hope to see further progress.

    Like or Dislike: Thumb up 17 Thumb down 0
  • Dah Menang Semua on Jan 16, 2025 at 6:31 pm

    No more excuse to skip
    parliament anymore

    Like or Dislike: Thumb up 13 Thumb down 0
  • Ajibkor sippimg Starbucks machiato on Jan 16, 2025 at 7:14 pm

    This unwanted lopsided ECRL costs a cool 55B to 60B easily.
    Subsequent govts after the 2018 elections have to honor the commitment with China,started by the recalcitrant dude.
    That kind of money spent could give us 50 new public hospitals.Now with thousands of medical policy holders letting their policies lapse,our public hospitals are overflowing and the waitng time for simple specialist appointments have stretched from 2 to 5 months.
    Make no mistake,the final ridership wont be better than our double tracking trains.
    Also,the hundreds of landowners who have their land acquired,almost slashing their valuation by half..can anyone sympathise ,to make way for a project we NEVER needed.
    Remember,WINNERS TAKE ALL( NOT US ).

    Like or Dislike: Thumb up 3 Thumb down 19
    • Centurion on Jan 17, 2025 at 12:07 am

      Dont give us your moral type of crap speech…ECRL is one of the most important project for this country, which will helps to develope East Coast region. It surely will create alot of jobs opportunities…Give some fairness to the east Coast people please…

      Like or Dislike: Thumb up 9 Thumb down 2
      • Akmal salleh Sr on Jan 17, 2025 at 5:37 pm

        The east coast people deserve not this train,but more hospitals,schools for underachievers,more drug rehab centres,more hiv prevention facilities.NOW Karak highway is being expanded.Just watch,only during Festive seasons,ridership is full,other than that,only some cement,farm animals make up the volume.Lots of jobs?Most of the skilled workers operating the China machines from where? If u spend that kind of money building more hospitals,I agree locals benefit more.Now,even the trains from China costs a bomb to operate.Even HSR Pmx dare not involve govt funds.Sir,your reasoning seems a lot more crap .

        Like or Dislike: Thumb up 4 Thumb down 3
  • Adora Flora City on Jan 17, 2025 at 2:11 pm

    Hope can board the beauty from Kuantan Port.

    Company Annual Dinner in Yuhudi Club Cherating make easier.

    Like or Dislike: Thumb up 0 Thumb down 0
 

Add a comment