PLUS Kulai-Sedenak extra lane works will be stopped from Jan 23 for 12 days, to ensure smooth CNY traffic

PLUS Kulai-Sedenak extra lane works will be stopped from Jan 23 for 12 days, to ensure smooth CNY traffic

The extra lane upgrade works on the PLUS Kulai to Sedenak stretch will be temporarily stopped for the Chinese New Year and school holiday period to smoothen traffic flow on the North South Highway, works minister Datuk Seri Alexander Nanta Linggi announced.

The pause on works will be for 12 days, from January 23 till February 3. The minister said that as of December 31, 2024, the PLUS Kulai to Sedenak extra lane project’s progress is at 5.02%, and the rest of the works there that started in July last year are progressing smoothly.

The extra lane will make it three lanes on each bound, one more than the current two lanes each. Phase 1 will cover a distance of 22 km from Sedenak to Senai Utara. The RM525 million project is split into two packages – Sedenak to Kulai, and Kulai to Senai Utara – and is expected to be completed by January 2028.

Looking to sell your car? Sell it with Carro.

10% discount when you renew your car insurance

Compare prices between different insurer providers and use the promo code 'PAULTAN10' when you make your payment to save the most on your car insurance renewal compared to other competing services.

Car Insurance

Danny Tan

Danny Tan loves driving as much as he loves a certain herbal meat soup, and sweet engine music as much as drum beats. He has been in the auto industry since 2006, previously filling the pages of two motoring magazines before joining this website. Enjoys detailing the experience more than the technical details.

 
 

Add a comment

required

required