Jalan Batang Kali-Genting Highlands route to fully open by May 2024 – slope repair now 38.6% completed

Jalan Batang Kali-Genting Highlands route to fully open by May 2024 – slope repair now 38.6% completed

The Jalan Batang Kali-Genting Highlands route is expected to be fully open to the public by May 2024, as repair works are expected to be completed in March the same year. This was revealed by Selangor Infrastructure and Agriculture Committee chairman Izham Hashim, as reported by Bernama.

The route (state road B66) was closed in December last year following a deadly landslide that hit a campsite at Father’s Organic Farm in Batang Kali near Genting Highlands. Later in January 2023, one lane of the B66 was reopened but not to all traffic as only motorists who met certain conditions (working in the Genting Highlands area with a validation letter) were allowed to use the route.

“We started repairing the slopes on May 28, and expect it to be completed on March 29 next year. We will consider reopening the road to Genting Highlands when everything is ready, said Izham.

“We have also researched the appropriate engineering method, and found that the TerraLink wall system design is the most suitable for the conditions of the site, which is quite narrow,” he continued, adding that the slope repair and stabilisation work is 38.6% completed so far.

Looking to sell your car? Sell it with Carro.

Certified Pre-Owned - 1 Year Warranty

10% discount when you renew your car insurance

Compare prices between different insurer providers and use the promo code 'PAULTAN10' when you make your payment to save the most on your car insurance renewal compared to other competing services.

Car Insurance

Gerard Lye

Originating from the corporate world with a background in finance and economics, Gerard’s strong love for cars led him to take the plunge into the automotive media industry. It was only then did he realise that there are more things to a car than just horsepower count.

 

Comments

  • Gumen on Nov 17, 2023 at 6:34 pm

    How did they determine such and exact 38.6% completion number? Sounds rather arbitrary.

    Like or Dislike: Thumb up 8 Thumb down 7
    • Easy...... on Nov 18, 2023 at 7:49 am

      Easy lah…as long as we as customer request for detailed/itemised/specific quote from supplier/vendor.
      A ‘simple’ repair job like this can have 20++ items in the quote or job requirement.

      Like or Dislike: Thumb up 0 Thumb down 1
  • bapak slow

    Like or Dislike: Thumb up 2 Thumb down 0
  • bapak slow

    Like or Dislike: Thumb up 1 Thumb down 0
    • Hmmmm on Nov 18, 2023 at 7:54 am

      Kebanyakan job di tempat2 sensitif memang slow kalau nk ikut cara kerja yang betul. Sebagai contoh, satu tapak projek bangunan bertingkat kat tebing sungai…pemaju sepatutnya tunggu untuk satu masa yg agak panjang selepas menambak tebing sungai sebelum start piling dan construct. Ko rase developer nak tunggu? Bila bangunan dh siap semua puji kata cantik…cepat…tanpa tau apa jadi kat foundation tu.

      Biasalah lumrah manusia….semua nak cepat. Time pancut je nak lambat.

      Like or Dislike: Thumb up 8 Thumb down 0
  • Eve, adams's second spouse on Nov 20, 2023 at 10:47 am

    Beware of mother nature wrath for destroying flora fauna, Titiwangsa mountain range is the spinal cord of southern part of south east asia peninsula

    Like or Dislike: Thumb up 2 Thumb down 0
 

Add a comment

required

required